Buying, Integrating and Replacing a Banking Platform: Planning, Testing and Cutover
Thirteen lessons on the riskiest project a bank runs - whether to replace at all, requirements that survive a vendor, the contract terms a supervisor expects, right-to-left planning and why it fails, testing environments that resemble production, governance that catches a decision, migration strategies, data and reconciliation, cutover, and a checklist drawn from a regulator's own findings.
Used in roles like Payments Operations Analyst · Settlement Officer · Payments Product Manager · Reconciliation Analyst
What the course covers
-
1. The riskiest project a bank runs, and the case we can actually read
Replacing a core banking platform or a payment switch is the most dangerous thing a bank does on
-
2. The decision before the decision
Before anything else: does the platform need replacing at all? This question is skipped more
-
3. Requirements that survive contact with a vendor
A requirements document is read by vendors who are expert at answering it. Most are written in a way
-
4. Running a selection
A selection is a decision-making process that happens to involve software. Run it as a process and
-
5. The contract, and what a supervisor expects to find in it
The contract is where a selection's findings either become enforceable or evaporate. It is also the
-
6. Right-to-left planning, and why the date is the danger
This lesson names the single most consequential anti-pattern in platform replacement, and it is named
-
7. Testing, and the risk of not testing
This lesson contains the most generalisable finding in the whole case, and it applies far beyond
-
8. Governance, and the decision that was never a decision
The findings on governance are the part of this case that transfers most directly to any institution,
-
9. Big bang, phased or parallel
There are three ways to move, and the choice is the programme's defining risk decision. Each is
-
10. Data migration, and the reconciliation that proves it
Lesson one said the most instructive fact in the case is that the data migration worked. This
-
11. Cutover, and rehearsing it until it is boring
The cutover is a few dozen hours in which the institution is neither on one platform nor the other.
-
12. Two platforms, and the exit that never happens
Whatever the strategy, there is a period with two platforms, and it lasts longer than any plan. This
-
13. The checklist the record produces
Everything in this course can be reduced to questions an institution should be able to answer in
Key terms
Why it is more dangerous than it looks · 5.2 million customers · December 2018 · £32.7 million · £48,650,000 in total · The data migration worked · Your data migration is necessary and it is not the risk · It took eight months to recover · does the platform need replacing at all? · Three honest reasons to replace · Three common reasons that are not reasons · And three alternatives that are almost never properly costed · Hollowing out · Upgrading in place · Fixing the configuration · And name who owns the outcome, not the project · The failure mode: functional lists · Four kinds of requirement that actually discriminate
Where this comes from
- Final Notice from the Prudential Regulation Authority to TSB Bank plc: the findings on outsourcing assessment, planning, testing and governance that this whole course is built on
- TSB fined £48.65m for operational resilience failings: the joint press release, with the penalty split, the customer numbers, the redress figure and the recovery period
- TSB fined for operational resilience failings
- Independent review of TSB's 2018 migration to a new IT platform, by Slaughter and May: published by TSB in November 2019. Listed so you can read it yourself - it is published in a form whose text could not be extracted for this course, so no finding here is drawn from it
- Guidelines on outsourcing arrangements (EBA/GL/2019/02)
- Guidelines on ICT and security risk management (EBA/GL/2019/04)
- Regulation (EU) 2022/2554 on digital operational resilience for the financial sector: requirements aimed at information and communication technology third parties
- Principles for operational resilience