The riskiest project a bank runs, and the case we can actually read
Replacing a core banking platform or a payment switch is the most dangerous thing a bank does on purpose. The companion courses in this catalogue are about choosing the platform. This one is about surviving the change.
Why it is more dangerous than it looks. The institution is replacing the system that holds its ledger, while continuing to take deposits, make payments and answer to a supervisor. There is no pilot customer base that does not matter. There is no version of the project where failure is contained to a project team. And the work is done by people who, by definition, have not done it before at this institution.
Most writing on the subject is either a vendor's methodology or a war story. This course uses something better: a regulator's findings, in a legal document, about a real migration that failed.
The facts, from those findings. In April 2018 TSB Bank migrated its customer and corporate services to a new platform. The data migrated successfully and the platform then immediately experienced technical failures. All of the bank's branches and a significant proportion of its approximately 5.2 million customers were affected. Some problems persisted, and it took until December 2018 for the bank to return to business as usual - eight months after a migration weekend. The bank paid £32.7 million in redress to customers who suffered detriment.
In December 2022 the two regulators fined the bank £48,650,000 in total - £29,750,000 by the conduct regulator and £18,900,000 by the prudential one, both figures already reduced by a 30 per cent discount for settling. The stated grounds were operational risk management and governance failures, including the management of outsourcing risks. The prudential regulator found breaches of two of its Fundamental Rules: the requirement to conduct business with due skill, care and diligence, and the requirement to organise and control affairs responsibly and effectively with adequate risk management systems.
Three things to notice before the detail, because they shape how the rest of this course is built.
The data migration worked. That is the single most instructive fact in the whole case. Almost every migration programme spends its anxiety on whether the records will arrive correctly. Here they did, and the programme still failed - on configuration, on readiness, on testing and on governance. Your data migration is necessary and it is not the risk.
The failure was found in planning and governance, not in code. Read the findings and they are about how a date was set, what was escalated, what was assessed about a supplier, and which forum took a decision. Those are management activities, available to any institution to do well, and they cost nothing but attention.
It took eight months to recover. Not a weekend, not a fortnight. Whatever your rollback plan says, plan for the possibility that you are living with the consequences into next year, and ask what that means for your capital, your people and your customers.
About the sources. The migration examined through this course is TSB Bank's move to a new platform in April 2018. Two documents carry the analysis: the Final Notice from the Prudential Regulation Authority to TSB Bank plc, dated 20 December 2022, and the joint Financial Conduct Authority and Prudential Regulation Authority press release of the same date. Both are public, both are linked in the sources, and every finding in this course is from them. TSB also published an independent review by Slaughter and May in November 2019, which is linked as well - but that document is published in a form whose text could not be extracted for this course, so no finding here is attributed to it. This course is not affiliated with any party named in it, and the regulators' findings are quoted as findings about one firm, not as a general claim about anybody.
The decision before the decision
Before anything else: does the platform need replacing at all? This question is skipped more often than any other, because by the time a programme has a name it has already been answered.
Three honest reasons to replace. The platform cannot do something the institution must do, and cannot be made to. The platform cannot be supported - the vendor has ended it, or the skills no longer exist, or the hardware does not. Or the cost of change through the existing platform has risen so far that ordinary product work is no longer possible.
Three common reasons that are not reasons. The platform is old; age is not a defect, and the companion course on core banking platforms shows four architectural generations all still running money. A new chief executive or chief information officer wants a signature programme. Or a vendor has made a compelling case, which is their job.
And three alternatives that are almost never properly costed.
Hollowing out. Move the work that changes often - payments, cards, onboarding, fraud, channels, reporting - out of the platform and leave the ledger where it is. The companion course covers the trade-off. It is slower to describe and far less risky to do, and it frequently delivers most of what the replacement was going to deliver.
Upgrading in place. If the institution is several versions behind, the gap between where it is and where the vendor's current release sits may be smaller than a replacement - and the upgrade path exists, which a migration path does not.
Fixing the configuration. Where the real complaint is that change takes too long, the cause is often modification, undocumented parameters and absent test environments rather than the platform. Those are fixable without a migration, and fixing them is a prerequisite for a successful migration anyway.
So the discipline for this stage is short and it is worth insisting on.
Write the problem statement before the solution, and make it measurable. Not "our core is legacy" but "we cannot launch a product in under nine months, we cannot support instant payments without a batch window, and three of our five mandatory regulatory reports are produced by hand." Those are testable claims. A replacement can then be assessed on whether it fixes them.
Price every option, including doing nothing, on the same basis. Over the same horizon, with the operating model, the integration estate and the risk included. Doing nothing has a cost and it is not zero; so does replacing, and it is rarely what the business case says.
And name who owns the outcome, not the project. A programme director owns delivery. Somebody on the executive has to own the institution's ability to operate afterwards, and that person should be the one deciding whether to proceed at each gate.
Requirements that survive contact with a vendor
A requirements document is read by vendors who are expert at answering it. Most are written in a way that guarantees a useless answer, and the fix is structural rather than a matter of effort.
The failure mode: functional lists. Several hundred statements beginning "the system shall", each answered yes. The document distinguishes nothing, and the institution has spent months producing a scoring exercise with no discriminating power.
Four kinds of requirement that actually discriminate.
Mechanism requirements. Not "can the platform support tiered interest" but "show us the mechanism by which tiered interest is defined, who in our organisation would use it, and what happens on upgrade." The companion courses call this scoring the configuration surface; it is the single most predictive thing you can measure.
Constraint requirements. The things that eliminate rather than score: entity, currency and country matrix, data residency, deployment models permitted by your supervisor, the hardware security modules you own, the endpoints you must connect to. Put these first and some candidates disappear before anybody writes a scoring spreadsheet.
Operating requirements. What the institution must be able to do unaided after go-live: create a product, change a limit, add an endpoint, run a period close, produce a regulatory return, restore a database, investigate a customer's transaction. For each, who does it and whether a vendor is needed. This is the section most often missing, and the one that decides life after the programme.
Evidence requirements. What the platform must be able to prove: the state of a record at a past date, who changed a parameter and when, the reconciliation of one figure to another. Lesson ten depends on these entirely, and so does every future examination.
Then write the scenarios, and keep them. Twenty to forty end-to-end cases drawn from your real business, including the awkward ones: a backdated transaction, a reversal across a period end, a multi-currency posting, a customer with one of everything, a leap-year accrual, a dormant account reactivated, a court order. These scenarios are used three times - in the demonstration you control, in acceptance testing, and in the dress rehearsals of lesson eleven - which is why writing them early pays three times.
One warning that comes straight from the record. A requirements process also produces the institution's first assessment of the supplier, and the regulator's findings in the TSB case are explicit that the firm did not formally and comprehensively assess whether its supplier had the ability, capacity, resources and appropriate organisational structure to deliver the platform in the timeframe adopted, nor the readiness to run it afterwards. That assessment is a requirement activity, it must be written down, and it is about the supplier's capacity to do this work on this timetable - not about the product.
Running a selection
A selection is a decision-making process that happens to involve software. Run it as a process and the decision is defensible; run it as a series of meetings and the loudest vendor wins.
Fix the weights before you see anything, and derive them from your own balance sheet. Publish them internally. Do not change them after a demonstration without writing down why. This is the companion courses' rule and it exists because persuasion is the vendor's core competence, honestly exercised.
Separate the teams and the questions. Commercial, functional, technical, security, operations and legal each have questions that the others cannot judge. Let each ask its own and score its own. The common failure is a technical team that never asks about the operating model and a business team that never asks about key management.
Control the demonstration. Your scenarios, your data, your sequence, your awkward cases. A vendor demonstration is a rehearsed performance of a happy path; you learn nothing from watching it that you could not have read. Insist on driving.
Interview the implementation partner separately, and the named individuals. The people who will actually do the work have different incentives from the sales team and a more accurate view of what configuration will cover. Ask who specifically will be assigned, for how long, and what else they are committed to.
Call references and ask only about the hard parts. What did the configuration not cover. What did you modify and do you regret it. What happened at the first period end. How long until you could change things yourselves. What would you do differently. Ask for a reference whose entity, currency and country matrix resembles yours, not whose volume does.
Assess the supplier's capacity, in writing, as its own deliverable. Not the product - the organisation. Does it have the people, the structure and the capacity to deliver on the timetable proposed, and to run the service afterwards if it is running it? The TSB findings treat the absence of that formal, comprehensive assessment as a breach, so treat its presence as mandatory. Record the evidence, the conclusion and the date.
Then build the costed comparison over the full horizon - licence or subscription, implementation, integration, upgrades and their testing, infrastructure, the operating model with real headcount, exit, and a realistic allowance for the modifications you will make despite intending not to.
And gate the decision. A selection should end with a recommendation, a dissenting view if there is one, the risks accepted, and an executive owner who signs. A decision nobody signed is a decision nobody owns, and this programme will need an owner for years.
The contract, and what a supervisor expects to find in it
The contract is where a selection's findings either become enforceable or evaporate. It is also the point at which outsourcing rules apply, and a platform is a critical or important function under any framework you are likely to be subject to.
Start from the supervisory expectations. European supervisory guidelines on outsourcing require a firm to remain fully responsible for complying with its obligations, to assess criticality, to conduct due diligence, to hold specified contractual rights including audit and access, and to maintain a documented exit strategy. The European Union's operational resilience regulation adds requirements aimed specifically at technology third parties. The Basel Committee's principles for operational resilience point the same way. Delegating the work never delegates the accountability, and a contract that reads as though it does will not survive a review.
Then add what the TSB record says was missing, because these are not theoretical.
Ongoing reassessment, not one-off diligence. The findings state that the firm did not formally and adequately reassess its supplier's ability and capacity on an ongoing basis, including in the light of service level breaches it had already encountered during earlier staged events. So the contract and the governance around it must require reassessment at defined points, and the institution must act on it.
Formal assurance in the form of statements of fact. The findings are precise: the firm did not receive formal assurance from its supplier in the form of statements of fact about the completeness of readiness activities already undertaken. A verbal reassurance in a steering meeting is not that. A signed statement, naming what is complete, is.
Fourth parties. The same findings name the firm's critical fourth parties - its supplier's suppliers - and fault the absence of assurance about whether the supplier had robust testing, monitoring and control over them. Your contract has to reach through your vendor to the parties it depends on: who they are, what happens if one fails, and what your vendor is required to tell you.
Service levels that are tested before they matter. The findings note performance and service issues with earlier staged events, which in some instances led to slow recovery from incidents and breaches of service level agreements. Those breaches were evidence available before the main event. Write service levels that produce evidence during the programme, not only after go-live.
Four more terms worth insisting on, which cost nothing at signature and a great deal later.
Named people, with a commitment. The individuals assessed during selection, with notice periods and replacement rights.
Access to the platform's own evidence, including the ability to extract your data in a documented format, on demand, without a project.
A priced, rehearsed exit. Lesson twelve. If exit has never been described in detail it does not exist.
And remedies tied to readiness, not to dates. A penalty for missing a date encourages a supplier to declare readiness it does not have. That is the incentive that produced this entire course.
Right-to-left planning, and why the date is the danger
This lesson names the single most consequential anti-pattern in platform replacement, and it is named because a regulator named it.
The two directions. A left-to-right plan starts from the work: what has to be done, in what order, with what dependencies, and derives an end date from it. A right-to-left plan starts from a target date and works backwards, fitting the work into the time available.
Everybody knows this. The reason it is worth a lesson is that the record shows what happens when a sophisticated institution does it anyway, twice.
What the findings say. The programme's original plan, adopted in March 2016, set a main migration event for November 2017. That plan was described as "aspirational" and reflected a top-down, "right-to-left" approach to planning to meet the target migration date. A left-to-right plan was developed afterwards and reviewed by a third party. The regulator's conclusion on the first plan is blunt: the right-to-left approach set an overly ambitious timetable for migration, given its scale and complexity, and the degree of operational risk.
Then it happened again. On re-planning in late 2017, the firm produced a new plan which, the findings say, also adopted an overly right-to-left approach. The regulator records that the firm took the view it would not migrate until it was ready - and still finds the planning insufficiently robust, because the re-planning did not adequately investigate the technical causes of the delays and did not adequately assess the service problems already seen, which should have caused the firm to question its supplier's readiness. The firm missed an opportunity to properly assess the extent of the delays, to learn the lessons from that assessment, and to realistically assess the volume of work remaining before it was migration-ready.
And one finding on its own line, because it is the most avoidable thing in this course. The firm publicly committed to a re-planned migration date before the re-planning had been completed or approved by its board.
Four rules follow directly, and none of them is difficult.
Derive the date from the plan, in public and in private, and never the reverse. If an external commitment exists - a vendor contract ending, a regulatory deadline, a separation agreement - then say so and treat the gap between that date and the plan's date as a risk with an owner, not as an instruction to compress the work.
A re-plan is an investigation first. When a programme slips, the first deliverable is an explanation of why, specific and technical. A re-plan that does not explain the slip will reproduce it, because the thing that caused it has not been identified.
Treat problems in earlier stages as evidence about the main event. Staged migrations, pilots and partial transitions exist to generate information. An institution that explains away their failures as teething has converted its early-warning system into reassurance.
Say nothing publicly about a date the board has not approved. A public date becomes a constraint on the institution's own decision-making, and it is the cheapest mistake on this list to avoid.
Testing, and the risk of not testing
This lesson contains the most generalisable finding in the whole case, and it applies far beyond banking.
What was found about the environments. The firm decided not to conduct non-functional testing of its digital channels in an active-active configuration across both data centres. The consequence, in the regulator's words, is that the testing and production environments were distinctly different, which meant that an opportunity to potentially identify some of the configuration issues experienced after migration was lost.
Note what that says. The records migrated correctly. The system then failed on configuration that a representative test would have had a chance of finding.
Now the part to carry into every project you ever run. The regulator found that the firm did consider that there were risks in conducting the performance testing in the live environment - so this was not negligence, it was a judgement. What the firm failed to do was identify and evaluate the risks of not conducting the testing, and it did not consider mitigants for those risks.
One side of the risk was assessed and the other was not. That is the lesson. Deciding not to test is itself a decision with a risk attached, and it has to be written down, evaluated and mitigated with the same seriousness as the decision to test. Almost no organisation does this, which is why almost every organisation has a production environment that differs from its test environment in ways nobody has assessed.
Five practices follow.
Enumerate the differences between test and production, deliberately, and keep the list. Data volume, data shape, configuration, topology, network, third-party endpoints, concurrency, hardware. For each, record the risk the difference creates and what compensates for it. The list is never empty; the point is that it is known.
Test the topology, not only the function. Failover, both data centres live, a node lost under load, a third party slow rather than down. These are the failures that arrive at go-live, and functional testing does not touch them.
Write the risk of not doing each test you decide to skip. One line each. This single habit would have changed the case this course is built on.
Use production-shaped data at production volume, with the privacy controls that requires. A platform that behaves well on a tenth of the data tells you very little.
And keep the scenarios from lesson three as the acceptance suite, run repeatedly and automatically, so that the thing you tested in week ten is still true in week sixty.
Governance, and the decision that was never a decision
The findings on governance are the part of this case that transfers most directly to any institution, because nothing in them required money, technology or unusual skill. They required somebody to be told something.
The decision that was taken in the wrong place. The firm had a forum for exactly this kind of choice. The regulator found that it failed to take a critical decision regarding non-functional testing in the Migration Testing Forum, which was the governance structure in place for such decisions. The governance existed. It was bypassed, and not maliciously.
Why it was bypassed. The risks were not identified in the final testing report, and so the decision was not escalated or sufficiently explained to the appropriate committees or decision makers, because this was viewed as purely technical and not presenting a risk to the firm. That sentence is the whole mechanism of the failure. The people closest to the decision classified it as technical. A technical classification routes a decision away from the people accountable for risk. The classification was the error, and it was made by people acting in good faith.
What the board did not get. The findings say it does not appear that certain matters were sufficiently discussed with the board, which could have led to challenge - specifically the overly ambitious timetable, deviations from aspects of the migration plans and guiding principles and what those meant for the programme's overall risk profile, and the readiness of both the platform and the supplier. Note the phrase "could have led to challenge": the regulator is not saying the board would have stopped it. It is saying the board was deprived of the chance.
And what the risk function did not do. The firm's risk management function did not adequately identify, assess and report on key risks, in particular operational risk related to the programme, and did not explicitly identify risks related to non-performance, or inadequate performance, of the firm's key supplier. The largest dependency in the programme was not on the risk register as a risk.
One more finding belongs here, because it is about the gap between a plan and its execution. Testing was executed in a manner which departed from the firm's stated plans and guiding principles, increasing operational risk. The institution wrote down how it would test and then did something else, and the deviation was not treated as a change requiring a decision.
So, five governance rules, each of which is cheap.
Nothing is "purely technical" in a migration. Any decision that changes what is tested, what is deployed, or when, is a risk decision. Route it accordingly, and make that routing rule explicit in the programme's terms of reference.
Deviation from the plan is a decision, not an event. If the testing approach, the guiding principles or the scope changes, that is a change request with an owner and an approver - and somebody should be reporting the cumulative count of deviations to the board.
The key supplier belongs on the risk register, by name. Its non-performance is a risk. Its capacity is a risk. Say so, rate it, and report it.
Give the board the uncomfortable items as a standing agenda item. Timetable confidence, deviations, supplier readiness, test coverage against plan. Four lines, every meeting.
And record what was decided, by whom, on what evidence. A programme that cannot show its decision trail cannot explain itself afterwards, and afterwards is when the explaining happens.
Big bang, phased or parallel
There are three ways to move, and the choice is the programme's defining risk decision. Each is defensible and each has a cost that institutions systematically misprice.
Big bang. Everything moves in one event. The attraction is real: one cutover, one reconciliation, no period of dual operation, no synchronisation between two platforms, and no sustained cost of running both. The risk is equally real: the institution has one attempt, the blast radius is the whole customer base, and rollback after customers have transacted on the new platform is extremely difficult. TSB's was a single main migration event, and its branches and a significant share of its 5.2 million customers were affected at once.
Phased. Move in tranches - by product, by portfolio, by entity, by geography, or by customer segment. The blast radius of each event is bounded, and each tranche generates information about the next. The cost is that the institution runs two platforms for a long period, with the synchronisation, reconciliation and double operational burden that implies - and with the awkward cases concentrated in the final tranche, which is usually the hardest.
Parallel run. Both platforms process the same work, and the results are compared. The old platform remains the system of record until the new one has been shown to agree with it. This is the only strategy that produces direct evidence of correctness before the institution depends on it, and it is the most expensive - double processing, double infrastructure, and a comparison engine that is itself a system to build and reconcile.
How to choose, honestly.
Start from reversibility, not from cost. For each option, write down exactly what you would do at each hour of the cutover if it is going badly, and up to which point that remains possible. The strategy whose rollback you can actually describe is usually the right one.
Phase on a boundary your ledger respects. By entity or by product is usually clean; by customer segment is usually not, because customers hold several products and relationships cross segments. A phase boundary that cuts through a relationship creates a reconciliation nobody can do.
Price the dual-run period honestly and double your estimate of its length. Lesson twelve. The period during which both platforms run is where the budget actually goes, and it is always longer than planned.
And if you choose big bang, say so as a decision with its risks written down. That is the point of this course's central finding: the failure was not in choosing one option over another, it was in evaluating one side of a risk and not the other. A documented big-bang decision with an assessed downside is a professional act. An undocumented one is the thing regulators write notices about.
Data migration, and the reconciliation that proves it
Lesson one said the most instructive fact in the case is that the data migration worked. This lesson is therefore not an argument that data is the risk. It is about doing the necessary part properly, and then not mistaking it for the whole job.
Four activities, in order, and they are not interchangeable.
Profiling. Find out what is actually in the old platform before designing anything. Not what the documentation says: the real distribution of values, the records that violate the rules the system supposedly enforces, the duplicates, the fields repurposed years ago for something else, the accounts in states that should not exist. Every migration discovers these, and the only question is whether it discovers them during profiling or during cutover.
Cleansing, with a decision owner. Each class of bad data needs a named owner and a documented rule: correct it, migrate it as it is, transform it, or leave it behind. "Leave it behind" is a legitimate answer and it requires a retention plan, because the obligation to produce the record outlives the platform.
Mapping, field by field, under version control. Including every default, every derivation and every transformation. This document is the migration's specification, and its quality decides whether a discrepancy found at cutover takes ten minutes or ten hours to explain.
Reconciliation, which is the only thing that proves anything. Three levels, all of them necessary. Counts - the number of records of each type on each side. Totals - the financial sums, by currency, by product, by general ledger account, balancing on both sides and to the ledger. Specimens - individual records compared in full, chosen deliberately to include the strange ones: the oldest account, the largest balance, the customer with one of everything, the account in litigation, the one with a backdated transaction in the last period.
Then the rules that keep it honest.
Reconcile to the general ledger, not only between platforms. Two systems can agree with each other and both be wrong. The ledger is the control.
Automate it and run it every rehearsal. A reconciliation performed by hand at cutover will be performed badly, at four in the morning, by someone who has been awake for twenty hours.
Define the acceptance thresholds in advance, with a named approver for each exception class. A threshold decided during cutover is not a threshold; it is whatever the room can bear at the time.
And keep the old platform readable. Lesson twelve. For months afterwards somebody will ask what a record looked like before it moved, and the only acceptable answer is to show them.
Cutover, and rehearsing it until it is boring
The cutover is a few dozen hours in which the institution is neither on one platform nor the other. It is the most rehearsable part of the whole programme and the part most often rehearsed least.
Build the runbook as a timed, owned sequence. Every step, with a start time, a duration, a named owner, a prerequisite, a verification that it worked, and a stated action if it did not. Not a checklist - a plan with dependencies, where anybody can see what is blocking what.
Then rehearse the whole thing, end to end, more than once. A rehearsal is not a technical exercise with the migration scripts. It is the full sequence with the real people, the real clock, the real communications, the reconciliations run and signed, and the decision points actually taken. The purpose of a rehearsal is to become bored, because boredom at the third rehearsal is the only reliable evidence that the fourth - the real one - will be uneventful.
Rehearse the rollback, not only the roll-forward. An untested rollback is a hope. And establish the point of no return explicitly: the hour after which reversing costs more than continuing, stated in the runbook, agreed by the executive owner in advance. When that hour arrives at three in the morning it must not be a discussion.
Define the go and no-go criteria before the week begins, with named approvers and the evidence each requires. The criteria should include the reconciliation thresholds from lesson ten, the state of every endpoint, the readiness statements from lesson five, and the open defect position with severities. And they must include the right to say no - which means somebody has to be authorised to stop, and everybody has to know who.
Staff the hours, not the task. A cutover spans more than one shift. Plan the handovers, the rest, the food and the physical location. Fatigue causes the errors that happen after the migration technically succeeded, and this is a well-understood operational risk that programmes keep treating as heroism.
Plan the communications as part of the runbook. Customers, branches, the contact centre, correspondent banks, schemes, the supervisor. Contact-centre volumes rise before anything is visibly wrong, and the agents need to know what to say and what they will be able to see. TSB's recovery ran to eight months, and the part customers experienced was not the configuration - it was not being able to get an answer.
And plan for the day after, and the month after. Hypercare with named people and shortened escalation paths. The first period end on the new platform is a second event almost as significant as the cutover, and it should be rehearsed and staffed as one, because interest, statements, accruals and regulatory extracts all happen there for the first time with real money.
Two platforms, and the exit that never happens
Whatever the strategy, there is a period with two platforms, and it lasts longer than any plan. This lesson is about operating it and about ending it - and the second half is where institutions quietly fail.
Decide, in writing, which platform is the system of record for each thing, and for how long. Not "the new one, after migration" but a table: this product, from this date, record lives here. Where the answer is ambiguous for even one data type, two teams will give customers different answers.
Synchronisation is a system, and it needs an owner. If both platforms hold live data, something keeps them aligned, and that something has failure modes, a latency, a backlog and a reconciliation of its own. It is the most under-designed component in most migrations because nobody wants to invest in temporary software - and it is temporary software that is load-bearing for a year.
Reconcile between the platforms daily and watch it. During dual running, the pair of them is the ledger, and divergence is a live financial control, not a project metric.
Expect the operational cost to roughly double, and staff for it. Two platforms, two sets of incidents, two sets of changes, two reconciliations, two vendors. Teams are usually asked to absorb this while also delivering the migration, which is how the migration gets its errors.
Now decommissioning, which is the part that does not happen.
The institution is live on the new platform, the programme team is disbanded, the budget is spent, and the old platform is still running - because a report comes out of it, or a reconciliation needs it, or nobody is quite sure what else uses it. So it stays. It keeps its licence cost, its hardware, its support contract, its security patching obligation and its audit scope, and it slowly becomes a system nobody understands that still holds customer data.
Four things that prevent it.
Fund decommissioning as part of the programme, not afterwards. It is the last ten per cent of the budget and the first thing cut. Ring-fence it.
Inventory everything that touches the old platform before cutover - reports, extracts, interfaces, spreadsheets, that one month-end process in finance. The list is always longer than expected, and it is the decommissioning plan.
Separate archive from platform. The obligation is to produce records, not to keep a running system. Extract what must be retained into a form that can be read without the application, prove it can be read, and then the platform can go.
Set the shutdown date at the start and report against it. A date nobody committed to will not arrive. And when it does arrive, keep the archive and the evidence that the extraction was complete, because the supervisor's interest in those records does not end when the platform does.
The checklist the record produces
Everything in this course can be reduced to questions an institution should be able to answer in writing before it migrates. They are drawn from what a regulator actually found, which is why they are worth more than a generic maturity model.
On whether to do it at all. Is the problem statement measurable? Have hollowing out, upgrading in place and fixing the configuration been priced on the same basis as replacement? Who on the executive owns the institution's ability to operate afterwards?
On the supplier. Have we formally and comprehensively assessed whether it has the ability, capacity, resources and organisational structure to deliver on this timetable, and to run the service afterwards? Is that assessment written down and dated? Are we reassessing it at defined points, and acting on the result? Do we hold statements of fact about what is complete, rather than verbal assurance? Do we know who its critical fourth parties are, and what it is required to tell us about them?
On the plan. Was the date derived from the work, or the work fitted to the date? If we have re-planned, did we first investigate the technical causes of the delay? Have we committed publicly to any date the board has not approved? Are we explaining away problems in earlier stages as teething, or treating them as evidence?
On testing. Do we have a written list of every difference between our test and production environments, with the risk each creates? For every test we decided not to run, have we written down and evaluated the risk of not running it, and the mitigations? Are we testing the topology, under load, with production-shaped data?
On governance. Does any decision affecting what is tested, deployed or when, reach the risk forum - and is "purely technical" explicitly excluded as a reason not to escalate? Are deviations from the plan logged, counted and reported? Is the key supplier on the risk register by name? Does the board get timetable confidence, deviations, supplier readiness and test coverage every meeting?
On migration and cutover. Can we describe the rollback at each hour, and the point of no return? Have we rehearsed the whole sequence, with the real people, until it was boring? Are the go and no-go criteria written, with named approvers and a real right to say no? Is the first period end rehearsed and staffed as a second event?
On afterwards. Which platform is the system of record for what, and until when? Who owns synchronisation? Is decommissioning funded and dated? Can we read the old platform's records without the old platform?
And the closing thought. The case this course is built on cost one bank £48.65 million in penalties, £32.7 million in redress and eight months of disruption to millions of people - and the data migrated correctly. What failed was a set of judgements that cost nothing to make well: who to tell, what to write down, which risks to evaluate on both sides, and whether to let a date overrule the work. Those judgements are available to every institution, at any budget, on any platform. That is the encouraging part of a discouraging story, and it is the reason the findings are worth reading in full rather than summarised.
In Kenya. A platform replacement at a licensed institution is a supervisory matter as well as a programme: the Central Bank of Kenya supervises banks and, under the National Payment System Act and the National Payment System Regulations, 2014, payment service providers, and expects to be informed about material changes to critical systems and about outsourcing arrangements, with the institution remaining responsible for continuity, data access and audit rights. Customer data is subject to the Data Protection Act, which bears on test data, on any processing outside the country and on the archive in lesson twelve. The practical consequence is to engage the supervisor early and in writing - not at go-live - and to treat the readiness evidence in this lesson as something a supervisor may ask to see rather than an internal artefact.
Fifty questions
Answer all fifty questions, then check your answers. You need 45 out of 50 to pass and receive a certificate. If you score less, you will see which answers were right and wrong, and then go through the course again before you retake the check. Your answers, progress and times are kept only in this browser.
Your answers
Your certificate of completion
Enter your name as you want it to appear, then save the certificate as a PDF. In the print window, choose Save as PDF. A certificate is issued once per completion of the course.
Rate this course
How would you rate this course? Your rating is anonymous — just a number, with no name and no account.
Bring this to your team
Your colleagues can take this course too — it is free, needs no sign-up, and nothing they enter leaves their browser. If your institution wants the same ground covered as structured training for a team, with an instructor and your own cases, we run courses in a classroom or online for groups of ten or more.
Talk to us about training your team → See the paid courses →
Saolix does not record who takes this course, so it cannot verify these certificates. The certificate confirms completion of a free self-paced course and is not an accredited qualification.
Standards and frameworks covered
The published frameworks this course teaches toward. Saolix is not affiliated with, endorsed by or accredited by any of these bodies; naming a standard is a citation, not a claim about its author.
Sources
The official documents this course relies on. Laws and guidance change, so check the current version.
- Final Notice from the Prudential Regulation Authority to TSB Bank plc: the findings on outsourcing assessment, planning, testing and governance that this whole course is built on · Prudential Regulation Authority, Bank of England, 20 December 2022
- TSB fined £48.65m for operational resilience failings: the joint press release, with the penalty split, the customer numbers, the redress figure and the recovery period · Financial Conduct Authority and Prudential Regulation Authority, 20 December 2022
- TSB fined for operational resilience failings · Bank of England, December 2022
- Independent review of TSB's 2018 migration to a new IT platform, by Slaughter and May: published by TSB in November 2019. Listed so you can read it yourself - it is published in a form whose text could not be extracted for this course, so no finding here is drawn from it · Slaughter and May, published by TSB Bank plc, November 2019
- Guidelines on outsourcing arrangements (EBA/GL/2019/02) · European Banking Authority
- Guidelines on ICT and security risk management (EBA/GL/2019/04) · European Banking Authority
- Regulation (EU) 2022/2554 on digital operational resilience for the financial sector: requirements aimed at information and communication technology third parties · European Union, December 2022
- Principles for operational resilience · Basel Committee on Banking Supervision, March 2021
- Principles for effective risk data aggregation and risk reporting (accuracy and integrity, and the single authoritative source a migration has to preserve) · Basel Committee on Banking Supervision, January 2013
- Core Principles for effective banking supervision (Principle 25, operational resilience, and Principle 26, internal control and audit) · Basel Committee on Banking Supervision
- Principles for financial market infrastructures (Principle 17, operational risk: change management, testing and the recovery of operations) · Committee on Payments and Market Infrastructures and IOSCO, April 2012
- National Payment System Regulations, 2014 · Central Bank of Kenya